Buckhurst Hill office refurb, the client needed it to be completed in just 7 days! This very tight project took a lot of organizing, fast track deliveries, and precise scheduling of tradesmen. Also, at the last hour, the client realized their work tables were delayed for 10 weeks so we built them (minus 1 set of table legs due to go today) and still managed to stay within the 7-day schedule! Even with all the extras that were requested along the way, we are happy to say...WE DID IT! Our client is over the moon. Check out the before and after pics below, and the video on the next post ...what do you think? Bishop Ltd - When Performance Counts! 0208 926 2010