Hi everyone,
Hope you are all enjoying the sunshine. Been a while since I posted requesting advice, so here I go
Things are progressing, albeit at a slow pace. When I first met the builder, he promised the work would be completed by 6-8 weeks. It's now into the 8th week and looks like only 40% of the work is done. When I asked him for an end time, his answer was 'Not sure, loads of lads on summer vacations'
That was just before he left for 2-week vacation!
I don't mind actually, as long as the work is safe and sound. That's my main concern, especially since I noticed cracks in the joists after they drilled into them.
Please see some pics enclosed within, any comments would be much appreciated
Many thanks
Mel
HU-768402840Original Author